The City of Racine will begin a significant roadway reconstruction project on Main Street from Goold Street to Melvin Avenue starting Monday, April 21, 2025. The project will be completed in multiple phases and is expected to finish by the end of October 2025. Both the Goold Street and Melvin Avenue intersections will remain open throughout construction.
Phase 1 (Goold to Augusta Street)
This segment will be fully closed to traffic for complete reconstruction. Work will begin April 21 and is expected to be completed by June 21, allowing the road to reopen in time for the Lighthouse Run and Fourth of July events.
Phase 2 (Augusta to Melvin Avenue)
Begins Monday, July 7, and will be completed in two parts:
Residents and visitors are encouraged to follow posted signage and detour routes. The City appreciates your patience as we work to improve our roadways.